New School Build - Photo Gallery
A photographic update of how work is progressing on our new building. Piling for foundations should be completed in the next week, with concrete starting to pour in the next few days. Currently on track for steels to start going up in mid-October…
"The first concrete pour has taken place (22 lorries worth!), and foundations continue to be dug out and prepared. "
Time lapse video - September 2019 - October 2019
The first steels being lifted into place. 5th November 2019.
New build update 6.2.2020 - The whole of the steel frame is now up
|
June 2020